1. REFURBISHMENT
1.1. GENERAL.
This February has been more productive tan any other month,
as we hardly havent had any stop due to rainfall.
During this month we have mostly advance in the shaping of
holes 12, 14 & 15, drainage has been installed on holes 12 & 15,
irrigation system on holes 10 and 11 is very advance and we have the
construction of the recently approve weir on green 12 is very advanced. Bridges
on 18 and 15 are finished just needing them to be faced with stone, bridge on
17 is also in the very latest steps of construction.
1.2. RAIN.
February as commented earlier has been the less rainy month
out of all, just 20mm of rainfall that have just put the project on standby for
3 days. Next may find a schedule that shows how February has evolved:
1.3. EARTH
MOVEMENTS.
The main area pending of being finished is 13th hole at this
moment, this will be done once the big pile of top soil is been spread or moved
to other places of the site. For this reason this we anticipate this hole to be
shaped by the end of April. The are some small earth movements to be done in
the green 12 area and some others on hole 18 surrounding the bridges. This item
is accomplished in a 90%.
1.4. DEMOLITIONS.
All the entities demolitions are finished at present day, as
this month the old existing weir on 12 and the toilets on hole 16th have been
demolished. Only pending of demolishing are the cart paths on hole 13th and the old wooden bridge that crosses the
12th/15th.
1.5. SERVICES.
February has still followed the same trend as previous
months, we continue to find and repair sewage and piping that is in bad state.
This month we have refurbished the main manholes on hole 12th that were in a
very bad state, we have removed a spillway pipe that was underneath the 14th
green and we have installed two new ones to replace it. Another main manhole
has been installed to remove an existing one that was under new tees on 13th.
1.6. WALLS.
This February we have finished the recently approve
extension of the north wall of 15th hole lake. This was built to reduce the
amount of carry over the lake form 54m that the original design showed in the
plans down to 40,5m.
We have also started to build the new walls attached to the
new weir of 12th Green area. One of the two walls will be finished at an
earlier stage so that enables the shaper to start shaping the 12th green asap,
the wall opposite can get going. This walls, as the weir, have been properly
sealed with a liner making it waterproof resistant.
Works on walls of lake 18th were finished at the beginning
of February, these works have enabled us to restore a very much deteriorated
corner on the walls of new 17th tees, creating a very much more homogeneous
area esthetical -wise.
With the objective to prevent future damages due to strong
floods, a big concrete slab has been pored to avoid future erosions.
1.7. WEIR NEXT TO
12TH GREEN.
New weir on 12th began its construction this February. The
construction of this new weir enables the green to be surrounded by water, making the hole much more attractive,
nevertheless, we having replaced a technically non retainer water wall for a
waterproof wall.
1.8. ACCESS
THROUGH THE CLUBHOUSE.
We have also commenced with the access next to the
Clubhouse, from the main Clubs plaza through the ramp that drives all our
members to the driving range or to the back nine holes. This area was very
deteriorated, leading in damp problems beneath in locker rooms and
laundry, for this reason we have sealed
the full path way to solve this problem. For esthetical reasons we have chosen
the same cobblestone that actualy is installed in the main plaza to keep the
same look all the way through eyesight.
1.9. SHAPING.
We have significantly advance on this item, even do that
many of the shaping as occurred in places that needed modifications due to
designer reviews. Tees on hole 15th have been modified, 12th has been
completely shape except the green that is pending on the finishing of the wall
attached to the new weir, tees, green and bunkers on 16th hole have been
shaped, first half of 15th and complete 14th have been shaped. Present day the
shaper only has pending to be shaped, green 12, approach area on hole 17th,
18th fairway and its bunkers and full 13th hole. Shaper may need to modify some
of these areas if designer is not happy after his future revision.
1.10. DRAINAGE.
We have been advancing and we have been able to recover some
delay of the drainage system, installing catch basins and land piping. We have
finalised this type of works on holes 10, 11, 12, 16, 17, 18 and partially on
hole 15. Almost a 45% of the drainage has been dealt vs. the 70% we should have
accomplished by now, we will keep recovering time on this item the coming days
to catch up with schedule.
1.11. IRRIGATION
SYSTEM.
We began to install irrigation system, installing main
piping for the ring of green complex on 18th going all the way down to 15th
going around 16th, this will improve the water pressure in this area that
always was a problem at the past. 10th hole has also been completed just
pending to finalise the tee area due to a final revision of the designer that
has finally approve this area. Greens 15th and 18th have been completed.
1.12. BRIDGES.
These have advance significantly this last month, having
nearly finish those on holes 15th and 18th only them waiting for the concrete
to settle to accomplish the resistance tests and facing them with stone.
Bridge on 15th:
As the original installation of pavement on cart path didn’t
include the slurry finishing, G&G has hired a specialized team to deal with
the cart paths and to give the same look to the cart path pavement of the
bridges, this way the cart paths will have the same look all the way through
being consistent with the look of the new cart paths.
Bridge on 17th:
Considering that the other two bridges had full priority,
17th was left to be dealt later, and for this reason it is in its early stage
of construction. Footings have been installed and actually they have pored the
concrete of the upper deck, the work should be finalized next week, just
needing the concrete pored left to settle for the next 3 weeks and facing it
with stone.
1.13. GREENS.
After some quality control tests, the gravel that was initially installed on
greens, had to be replaced as the gravel had an excess of fines and didn’t meet
with the USGA specifications. At present day, greens 10, 11, 15, 17 & 18
are fully drained and gravel has been layed.
Regarding Sand mix for greens, we have done our preliminary
quality control tests to our first loads of which they result weren’t fully
successful has they had small deficit of organic matter. This has been informed
to the provider that has corrected before mentioned levels of organic matter. A
sample has been sent to the European Turfgrass Laboratory (Scotland) for its
approval on USGA green mix spects.
1.14. BUNKERS.
We are ongoing with the construction of bunkers and
re-facing with topsoil those bunkers that have already been shaped. Bunkers on
holes 10, 18 and 15 are ready and also been mark by the designer with the
grassing lines, at his last visit.
1.15. TEES.
We have installed tee platforms and its drainage system on
all those tees that the designer has approved. This operation needs to be done
with a laser leveller to obtain the desired grading to be able to perfectly
drain the playing surface.
Tees on 11th , 16th and 18th have been drained. Tees on
holes 15th and 12th even do they are finished shaping wise, now that they were
approved by the designer in his last visit, now will be also drained. Tees on
14th and 17th will follow the same process as they have been already rough
shaped.
1.16. CART PATHS.
We have already done a tester cart path near the green
complex on hole 18th, it has been really satisfactory for the property, project
manager and designer. It has been approved so rest of them to be built will
follow same specifications. No more areas have been built do we needed to approved
the location of them together wit the designer. Next paths to be built will
happen on holes 10th, 14th, 15th & 18th.
1.17. DESIGNER LAST
VISIT.
Kyle Phillips spent some days with us, from the 5th till the
9th of March, during his time here he was able to revise and approve the
shaping that has happened during this last month. Along in his visit some of
the features have been modified such us:
• Green &
bunkers on hole 16th to be able to place them nearer to the water edge.
• Addition of
a Professional back tee for hole 17th
• Modifying
the 12th fairway bunker and the grading of the left side of the fairway.
• Left side of
the landing area of hole 15th to make it higher.
• Connexion of
cart patsh on tees 12th/6th
• Access to
the clubhouse, 10th tees and new chiringuito area.
• Cart path of
hole 16th.
• Bunker
between 11th green and back tee on 12th
During his last visit we have advance on several aspect
regarding definition of grass areas, bunker lines, grass lines, cart path
planning and some strategic tree planting.
2. EVOLUTION OF
THE PROGRAM SCHEDULE.
This chapter includes a table were you may be able to
foresee the progress item by item. The table shows the % of progress vs.
schedule.
We here by summrise in a calendar Schedule working/stopping
days: