1. PROGRESS REPORT.
1.1.
GENERAL.
Significant
progress has been made in April due to the scarcity of rain and to the
Contractor’s increased production.
The works
carried out in April are the modification of the shaping of the hole 16th, the
platform for professionals of the hole 17th, the modification of the tees of
the hole 14th, the modification of the tees of the hole 15th and the
modification of the green of the hole 14th. The irrigation of the holes 10th, the
northern area of the hole 11th, the northern side of the hole 15th, and the
green of the hole 18th has been completed. The works on the hole 16th and the
green of the hole 11th – the tees of hole 12th are now being finished. The
construction of the dam and walls next to the green of the hole 12th is
finished, being the covering with stone of the dam outstanding, together with
some adjustments to improve waterproofing. The three bridges are being covered
with stone and this is the last phase of their construction, giving us more
time for the rest of the works.
After having
tried to recover the delay up until today, a matter that is beyond all parties’
control, The Work Management is of the opinion that the works will end 6 weeks
after the date foreseen.
1.2. RAIN.
Good progress
was made in April due to the lack of rain. It only rained twice and the
rainfall was 8 mm, therefore, no days of work were missed.
Rainfall
registration chart in April 2015:
1.3. EARTH MOVING.
The main
outstanding area is the hole 13th, where the earth moving of the tees is
already finished. Some other areas of this hole are pending, as we must wait
until the topsoil lamination of the roughs is done, the existing stockpile
used, and the installations - whose elements (irrigation pipes, chests, wires,
sand, gravel, etc.) cannot be piled at other areas - are finished. The
percentage of completion of this chapter is 95%.
1.4. DEMOLITION.
This chapter
is almost finished. Only the demolition of some buggy paths next to the holes
12th and 13th is outstanding. The fixing of the stream, which is also pending,
will take place at a later time.
1.5. SERVICES AFFECTED.
The reparation
of the services damaged by the works, or those in bad condition went on in
April. This month we continued working on the sewerage system of the hole 13th.
At the end of
April, we covered the trench of the hole 18th, which was used as a bypass for
the lake next to the hole 18th and was necessary to undertake the modification
of both this hole and the bridge.
1.6. MEDIUM VOLTAGE NETWORK.
The medium
voltage network used for the course pumping station was modified in April, as
the refurbishment works had affected it. New cables were laid, being the old
ones damaged, and a new channelling of the electrical wiring took place for it
to be protected and identified.
1.7. WALLS.
The walls
closing against the bridge of the hole 18th and situated next to the tee of the
hole 17th, were finished this month. The covering of the dam next to the 12th
green with stone is also finished.
1.8. SHAPING.
The main
shaping works carried out in April are:
• The tees of the hole 13th
• The green of the hole 12th
• The green of the hole 13th
• The holes 14th and 17th
• The modification of the buggy paths
next to the holes 12th, 15th and 16th
• The modification of the greens and
tees that form the hole 14th
1.9. DRAINAGE SYSTEM.
The drainage
system of the hole 14th were partially carried out in April. The drainage of
the holes 10th, 11th, 12th, 15th and 16th is already made. Some small stretches
are pending, together with the bridges of the holes 14th, 15th, 17th and all
areas of the holes 13th and 18th.
1.10. IRRIGATION.
The
installation of the irrigation system pertaining to the holes 12th and 17th
continued in April. The following areas are already finished: the holes 10th,
11th, 12th, the northern side of the hole 15th, the hole 16th, and the 18th
green. Presently it is being completed on the holes 17th and 14th.
1.11. BRIDGES.
The covering
with stone of the bridges was finished in April. The outstanding work under
this chapter is the connection of the buggy paths to the platform of the
bridges. It will be carried out when the execution of the different buggy path
stretches inside each area takes place.
1.12. GREENS.
The lamination
of the greens with the mixture of sand and peat selected for this project
started in April. The sand is already laid on the greens 10th, 15th, 16th and
18th and will be shortly laid on the greens 11th, 17th, 14th and 12th.
1.13. BUNKERS.
The slopes of
the bunkers of the holes 10th, 16th, 18th and 15th are being overlaid with
topsoil.
1.14. TEES.
The lamination
with sand of the tees started in April. It is already finished on the tees of
the holes 10th and 17th and will be soon carried out on the 16th, 11th and
12th, adhering to the seeding order foreseen.
1.15. BUGGY PATHS.
Some buggy
paths next to the hole 16th were completed in April, together with some
stretches that were renewed next to the holes 6th and 18th.
2.
WORK PROGRESS ANALYSIS.
The charts in
this chapter show the evolution of the different construction works included in
this project. It shows the progress of the different works grouped in chapters
and compared with the schedule initially foreseen. It shows also the percentage
of work already performed at any given certification date and the delay or
advancement attached to them. Likewise, it is possible to identify other works
started ahead of schedule representing an advance on what was planned.
The chart
below shows the amount of work executed by the 1st of May. At this
certification date the chapters being finished are earth moving, shaping,
demolition, works on lakes, the dam next to the green 12th; the accesses to the
club house and the bridges. Likewise, the works being executed are irrigation,
drainage and overlaying of fairways and roughs, together with the seeding of
the first holes, foreseen for the week in which this report was written.
As already
informed in previous reports, after the delay caused by a series of
circumstances, the Contractor has been requested a new execution calendar and
more means conducive to work completion.
The calendar should allow seeding at the end of June. A total of 42
persons work presently on the course and the Contractor confirmed that this
figure would be increased with further incorporations foreseen for the coming
weeks.
The chart
below summarizes the cumulated days in which it was impossible to work from the
1st of September, the anticipated date of commencement.
From the first
of September the land received a total of 510 litres of water per square meter.