20 DIC - 23 DIC

domingo, 29 de septiembre de 2024

 

WORKS IDENTIFIED BY MAINTENANCE DEPARTMENT TO BE ACCOMPLISHED IN THE NEAR FUTURE

Red: in process. Green: completed

PRIORITY

Raise low drains and irrigation boxes

1

Staples to reinforce signing

1

Edging woodchip areas

1

Drain 9/Driving Range

1

Repair municipal waist system at 6

1

Review tee contour

1

Raise sleepers at 15-12 path

1

Review and clean satellites

2

Transitioning Zoysia collars on putting greens

3

Install sleepers in bark area 1-9

3

Mow steep banks 1,3,6,7,8,11,12,16,17

Clean bark areas

Wash salts in bad areas

Wash salts in tees

Apply chlorine to control algae on bunkers

Plant SGA green 1 with bermuda

Gypsum application on roughs and fairways

Scalp roughs prior to maintenance week

Set-up protocole

FLOWERS:

Prune at green wall

1

Plant trees at 1 and 18

1

New bushes on lakes 1,6,7,8

1

Fix esparteras between tee and 12th fairway

2

Lentiscos in corner 2

3

Add woodchip

Prune yucas

Plant tree at 5

Add plants on Green Wall

Cut dead palms

FURNITURE:

Plant new bushes around lakes

1

Move furniture at 1st tee

1

install RCG Las Brisas billboards permanent anchors

2

Paint wooden bridge 17

3

Painting wooden handrail 18

3

Install bases for forniture at driving range

Clean and paint putting green wooden flags