There has been and increase of the pace of works in
the month of May, the absence of
Rainfall and the increase of manpower has been really helpful and productive.
During this month they have completed the complete
shaping of hole 18th, modification of green 13th and the
buggie paths of hole 17th. The stone walls in lakes 15th,
18th and 12th have concluded. Drainage on holes 18th,
greens 12th and 14th
has been installed, this operation has already started on hole 13th
with a installation going through a neighbour plot. Irrigation has been already
installed on holes 17th, 15th and partially on hole 14th.
Finally we have grassed hole 10th, half of the hole 11th
from tees to the lake, hole 16th and half of the hole 15th
from green down to the lake, also north tees of hole 17th have been
grassed.